Field Renovation Updates

Updates 9/30

Current Updates:

  • Turf Leveling: Final leveling has taken place and is ready for sod.
  • Grass: Seeding has taken place around the field and sod will be installed the week of 9/30 weather pending.
  • Walkway: concrete has been poured, The majority of work has taken place for the walkway around the field.
  • Plumbing/Electrical for Concession stand: Lines will be run to the field underground for the concession stand during fall break.